ContractingNovember 2024 – January 2025 · About 8 weeks
1,500 m² covered car park construction
We built the 1,500 m² covered car park of an industrial plant as a contractor. The job covered car park construction, drainage and surfacing works.
- Site preparation and excavation
- Steel mesh, concrete pour, surface finishing and joint cutting
- Removal of the existing canopy and erection of a new car park canopy
- Automatic gate, personnel gate, perimeter fence, mirrors and signs
- Car park floor painting
Completed and handed over within the agreed time and terms.
View the Contracting and Site Works: Roofing, Epoxy Flooring and Concrete service
RoofingMay – July 2025 · About 10 weeks
7,000 m² industrial roof repair
We repaired the 7,000 m² roof of a production plant as a subcontractor.
- Roof sheet replacement and repair
- Membrane and waterproofing
- Thermal and acoustic insulation
- Roof cleaning
Completed and accepted without defects.
View the Roof Cladding and Insulation service
Fabrication and installationAugust – September 2025 · About 5 weeks
Heavy-duty racking fabrication and installation
We fabricated and installed high-capacity heavy-duty racking for the warehouse yard of an industrial plant, designed in line with safety and quality standards.
- 3 levels, 6 bays, 18 racks in total; capacity of 36 pallets
- Rack bay size 270 × 150 × 100 cm, rack height 450 cm
- Storage platform measuring 700 × 350 × 300 cm
- Site measurement, cutting and fabrication in the workshop
- Primer and industrial paint
- Transport to site, installation and touch-up painting
Completed within the planned time and terms and accepted by the client.
View the Welding, Pipe Fabrication and Steel Structures service
Fabrication and installationMarch – May 2025 · About 10 weeks
Cyclone system design, manufacture and installation
As part of a process line improvement in a production plant, we designed, manufactured and installed a high-capacity cyclone system and its equipment.
- Design
- Manufacture in the workshop
- Installation on site
- Commissioning
Completed in full within the contract time and terms; commissioning after installation was successful.
View the Welding, Pipe Fabrication and Steel Structures service
Spare parts2025 · Made to drawing
Cutting blade in nickel-based superalloy
We manufactured a 2,380 mm long cutting blade for a production line from a technical drawing.
- Material: nickel-based superalloy (48% Ni – 28% Cr)
- Length: 2,380 mm
- Preparation of the technical drawing and manufacture
The part was manufactured and delivered.
View the CNC Machining and Spare Parts Manufacturing service